Users Online
· Guests Online: 15
· Members Online: 0
· Total Members: 188
· Newest Member: meenachowdary055
· Members Online: 0
· Total Members: 188
· Newest Member: meenachowdary055
Forum Threads
Newest Threads
No Threads created
Hottest Threads
No Threads created
Latest Articles
Articles Hierarchy
Isaca- CISA
Question ID 22457 |
A team conducting a risk analysis is having difficulty projecting the financial losses that could result from a risk. To evaluate the potential losses, the team should: |
Option A |
compute the amortization of the related assets. |
Option B |
calculate a return on investment (ROI). |
Option C |
apply a qualitative approach. |
Option D |
spend the time needed to define exactly the loss amount. |
Correct Answer | C |
Update Date and Time 2018-03-30 05:19:28
Question ID 22490 |
Before implementing an IT balanced scorecard, an organization must: |
Option A |
deliver effective and efficient services. |
Option B |
define key performance indicators. |
Option C |
provide business value to IT projects. |
Option D |
control IT expenses. |
Correct Answer | B |
Description A definition of key performance indicators is required before implementing an IT balanced scorecard. Choices A, C and D are objectives.
Update Date and Time 2018-04-03 06:30:53
Comments
No Comments have been Posted.
Post Comment
Please Login to Post a Comment.