Isaca- CISA
Question ID 22528 |
Which of the following is the PRIMARY objective of an IT performance measurement process? |
Option A |
Minimize errors |
Option B |
Gather performance data |
Option C |
Establish performance baselines |
Option D |
Optimize performance |
Correct Answer | D |
Update Date and Time 2018-04-04 05:09:38
Question ID 22529 |
Which of the following risks could result from inadequate software baselining? |
Option A |
Scope creep |
Option B |
Sign-off delays |
Option C |
Software integrity violations |
Option D |
inadequate controls |
Correct Answer | A |
Update Date and Time 2018-04-04 05:54:48